Chashma Nuclear Power Complex

Source :    Date : 12-May-2017

 

The Chashma Nuclear Power Complex near Chashma city,MIANWALI District, Punjab, Pakistan, is a commercial nuclear power generation complex, consisting of Chashma Nuclear Power Plant-I (CHASNUPP-I) and Chashma Nuclear Power Plant-II (CHASNUPP-II), with CHASNUPP-III and CHASNUPP-IV under construction. Chashma Nuclear Power Plant's reactors and other facilities are being built and operated by the Pakistan Atomic Energy Commission with Chinese support under the approval and guidelines of International Atomic Energy Agency .

 

The IAEA as well as the United States Department of Energy recognize the urgency of Pakistan's energy needs, which are expected to grow seven to eight times by 2030.

 

In November 2006, The International Atomic Energy Agency approved an agreement with the Pakistan Atomic Energy Commission for new nuclear power plants to be built in the country with Chinese assistance. The 35-member Board of Governors of the IAEA unanimously approved the safeguards agreement for any future Nuclear Power Plants that Pakistan will be constructing.

 

Chashma Nuclear Power Plant I

The 325 MW Chashma Nuclear Power Plant I is a pressurized water reactor that began commercial operation in May 2000.[3] It is located at Kundian, Punjab, Pakistan.

 

Chashma Nuclear Power Plant II

The 340 MW Chashma Nuclear Power Plant II, like CHASNUPP-I, is part of the Chashma Nuclear Power Complex in the northwestern region of the Thal Doab. The site is located south of Mianwali, near the Chashma Barrage and on the left bank of the Indus River.

 

The 340 MW Chashma Nuclear Power Plant II was officially inaugurated on 10 May 2011 by former Prime Minister Yousaf Raza Gillani.

 

Chashma Nuclear Power Plant III and IV

On April 28, 2009 a general engineering and design contract for CHASNUPP-3 and CHASNUPP-4 was signed with Shanghai Nuclear Engineering Research and Design Institute (SNERDI). The units will both have generation capacity of 340 MW and a design life of 40 years.

On 6 March 2013 the dome of the third reactor was lifted into place. Construction is planned to be completed in 2016 for No. III, and in 2017 for No. IV.

Chashma Nuclear Power Plant V

On March 2013, Pakistan and China agreed to build an ACP 1000 MW CHASNUPP-5 at Chashma Nuclear Power Complex.